enum GmbH - Datacenter power supply – Maintenance details
All systems operational
Datacenter power supply
Completed
Scheduled for February 09, 2026 at 2:00 AM – February 10, 2026 at 4:00 AM
Affects
DNS
Under maintenance from 2:00 AM to 4:00 AM
Network
Under maintenance from 2:00 AM to 4:00 AM
Firewall
Under maintenance from 2:00 AM to 4:00 AM
Identity & Access
Under maintenance from 2:00 AM to 4:00 AM
Compute
Under maintenance from 2:00 AM to 4:00 AM
Kubernetes
Under maintenance from 2:00 AM to 4:00 AM
Updates
Completed
February 10, 2026 at 4:00 AM
Completed
February 10, 2026 at 4:00 AM
Maintenance has completed successfully
In progress
February 09, 2026 at 2:00 AM
In progress
February 09, 2026 at 2:00 AM
Maintenance is now in progress
Planned
February 09, 2026 at 2:00 AM
Planned
February 09, 2026 at 2:00 AM
Due to scheduled work by the local power grid operator, the data center location will temporarily operate on backup power systems (generator supply) during the above-mentioned period.
Power will be supplied by fully redundant diesel generators (at least N+1). The transition to backup power and the return to normal operation will be carried out in a controlled, step-by-step manner under continuous monitoring by the data center operator.
The data center provider does not expect any impact on services during these works. However, as a precaution, we would like to note that operations will be running outside of the regular normal state.
The data center operator will have additional specialized personnel on site throughout the entire maintenance window and will provide building-specific updates regarding each power transition.